So, this is where we are at.
1. OSD (Onsite Stormwater Detention) drawings are in the 'process' of being drawn up - should take 2 weeks - we signed off on the 'process' happening 1 week ago today, the block was not saturated 2 weeks ago when it poured for most of the week. So I don't know why we will require the OSD - when ALL downpipes go into 10,000 litre water tank to be used in the home for toilets and washing. I could understand if the land was across the road, those blocks are like a mud bath, but hey thats what you get for buying a sloping towards rear block, on the low side of the street.
2. Apparently McDonald Jones have 'all' the paperwork.
3. We have received correspondence for block across road and one down for review from council. NO OSD papers attached. Cant understand why this one is so far ahead - when we hear through the grapevine that their builder is going to start a class action against council and developers. Good luck with that. We gather this builder has at least another 10 blocks that we hear are going to have significant costs involved with OSD construction - some figures thrown around $50k for these ones.
1. OSD (Onsite Stormwater Detention) drawings are in the 'process' of being drawn up - should take 2 weeks - we signed off on the 'process' happening 1 week ago today, the block was not saturated 2 weeks ago when it poured for most of the week. So I don't know why we will require the OSD - when ALL downpipes go into 10,000 litre water tank to be used in the home for toilets and washing. I could understand if the land was across the road, those blocks are like a mud bath, but hey thats what you get for buying a sloping towards rear block, on the low side of the street.
2. Apparently McDonald Jones have 'all' the paperwork.
3. We have received correspondence for block across road and one down for review from council. NO OSD papers attached. Cant understand why this one is so far ahead - when we hear through the grapevine that their builder is going to start a class action against council and developers. Good luck with that. We gather this builder has at least another 10 blocks that we hear are going to have significant costs involved with OSD construction - some figures thrown around $50k for these ones.