Time Line

31 August 2016  Downpipes look like then have been connected. Looks like we are looked up - handle sighted on front door


30 August 2016 Front door installed, looks like almost locked up

30 August 2016 Site supervisor advised that lock up will be this week

27 August 2016 Waterproofing complete

26 August 2016 Roller door installation, sanding complete on gyprock

23 August 2016 Gyprock completed

17 August 2016 Insulation started, gyprock delivered, cornice delivered

17 August 2016 Progress Invoice Issued

30 July 2016 Met with Landscaper

July 2016 Roof Complete - 8 roofers onsite

22 June 2016 Frame Complete

20 June 2016 Frame delivery

1 June 2016 Progress Invoice issued

30 May 2016 Slab complete

24 May 2016 Piering completed

August 2016 Electricial rough in


15 August 2016 Bricks cleaned

July 2016 Roof Delivered

4 July 2016 Bricks started

29 June 2016 Bricks delivered

18 May 2016 Site scraped

13 May 2016 Porta Loo delivered (Saturday)

12 May 2016 Red peg on block

11 May 2016 Attended MDJ to reselect new tiles for bathrooms & laundry since last ones were discontinued.

5 May 2016 Placed on the Construction List (Day 1)MDJ advised 2 x tiles no longer avail, one has direct replacement, need to choose new one.

4 May 2016 MDJ issued receipt for 1st Invoice

3 May 2016 MDJ received Construction Certificate

29 April 2016 Back colourbond fence installed

26 April 2016 MDJ sent 1st Invoice for payment MDJ received approved plans from Council

18 April 2016 DA Approved !

14 Mar 2016 Building Approval Application submitted 

2 Nov 2015 Land settled

30 Oct 2015 Settlement due Monday morning 2.11.15

14 Oct 2015 Told settlement on land due early November - asked to settle earlier.

13 Oct 2015 Real estate agent sends test msg - Stage 1 registered :) :)

MDJ advised they can now do their searches.


9 May 2015

Keep Out !!!



Fence on Main Rd


March 2015 almost ready to roll


The Block & Footpath

Facing East

Facing South East


15 October 2014 



17 August 2014 




Land Being developed

24/7/14 - Colour Selection Day 
4/7/14 - Colour Selection Centre walk through
June 2014 - deposit paid
End of May 2014 - received 1st quote for Summer House - with modifications
Mid May 2014 - request quote for Summer House
May 2014 - settled on builder and house plan