Monday, 18 July 2016

Brickwork


Brickwork was started on 4 July 2016.








Update 18 July 2016


Since the last update, a lot of things have happened

1. Concrete pits for Onsite Water Detention were delivered - I was told by the plumber that they sent the wrong ones. The correct ones came and have been put in place.
2. Frames were delivered on 20.6.16
3. Frames were completed 22.6.16
4. Bricks delivery 29.6.16 - only 4 pallets
5. Bricks started on 4.7.16

Since the brickwork has started 2 weeks ago now. A few days the brickies have not worked due to 'rain' or they did not appear on site.

Today is a day full of sunshine - after the Harbour city was covered in fog.



Frames delivered and spread out

Frames delivered and spread out

There she is... And her name is....

The Summer Room... 

Kitchen looking into Family room

Family room looking back to Kitchen / Dining

Kitchen / Dining looking to Kitchen and Alfresco area

Main Bedroom looking to entry alcove, WIR and to the right the Ensuite

Thursday, 2 June 2016

Update 2 June 2016



Thursday Update

1. Piering completed 24.5.16 - allowance 70lm - came in at 77.5lm - extra charge for 7.5lm.
2. Slab preparation work completed on Friday 27.5.16, Saturday 28.5.16 
3. SLAB POURED Monday 30.5.16
4. Progress Invoice issued 1.6.16

Photos dont do block justice, appears we have less yard than we really do due to angles lol.



Pier holes 

Front right side of house 

Pile of Dirt to be moved
Side of garage

Rear of house - pad for water tank

Front of house main bedroom drop edge beam




Monday, 23 May 2016

Monday Update


Events Recently

1. Site was scrapped on Wednesday.
2. Letter received stating Completion Date
3. Phone call just received (as I type this) piering tomorrow 24.5.16








Thursday, 12 May 2016

Update

On 11 May 2016, had to attend MDJ office to choose new tiles for Bathrooms and Laundry as tiles we picked sometime ago were discontinued. There is only a slight difference from the original pick.

See Below

Main Bathroom and Laundry - this shows benchtop & vanity colour




Ensuite - this shows Wall being white with marble through it, darker tile is the floor - also shows bench top & vanity colour.


The Red peg has arrived


The Red Peg has arrived today !!! Excuse the finger print lol


Monday, 9 May 2016

Construction List

6 May 2016

Put on the Construction List today.