Since the last update, a lot of things have happened
1. Concrete pits for Onsite Water Detention were delivered - I was told by the plumber that they sent the wrong ones. The correct ones came and have been put in place.
2. Frames were delivered on 20.6.16
3. Frames were completed 22.6.16
4. Bricks delivery 29.6.16 - only 4 pallets
5. Bricks started on 4.7.16
Since the brickwork has started 2 weeks ago now. A few days the brickies have not worked due to 'rain' or they did not appear on site.
Today is a day full of sunshine - after the Harbour city was covered in fog.
Frames delivered and spread out
Frames delivered and spread out
There she is... And her name is....
The Summer Room...
Kitchen looking into Family room
Family room looking back to Kitchen / Dining
Kitchen / Dining looking to Kitchen and Alfresco area
Main Bedroom looking to entry alcove, WIR and to the right the Ensuite