Tuesday, 30 August 2016

Update 30 August 2016

Tuesday Update

1. Site Supervisor advised should be at lock up this week.
2. Waterproofing complete 27.8.16
3. Gyprock finished and sanded 26.8.16
4. Garage roller door installed 26.8.16

Now that the walls are up you can really get a view of how the house size is. The frames don't give you any idea of how the house will feel. 

In recent weeks a few purchases have been made. 

1. Lounge suite for family room area.
2. Carpet
3. Bedhead and base


Decisions / Quotes have been received.

1. Tiles - Skheme
2. Retaining wall for OSD (onsite storm water detention)
3. Landscaping wall for side rear of house
4. Driveway